The Lavasa Environment Clearance in a Nutshell


 

The Background

March 2004

Lavasa obtains clearance from Government of Maharashtra for the first phase of 2000 ha

2004-2010

The developmental work starts. First town of Dasve nearly completed by 2010. During the course, GoM and MoEF grant additional clearances for laying transmission lines, road widening, tunnel construction etc.

 
 

The Issue

25th Nov 2010

MoEF unexpectedly issues a ‘Show Cause cum Stop Work’ notice to Lavasa. MoEF states that the required environmental clearances should have been obtained from MoEF and not from Government of Maharashtra. Lavasa files a Writ Petition in Bombay High Court challenging the notice.

Dec 2010 – Jan 2011

High Court directed MoEF to visit the project and inspect the same. Accordingly, the MoEF team visits Lavasa in the first week of January 2011.
Based on the report submitted by the team, MoEF mentions that they were willing to consider the project on merits provided Lavasa submits certain information for scrutiny.

Feb 2011 – Jun 2011

Lavasa submits various documents to MoEF for their consideration. Lavasa also addresses a letter to MoEF for finding an amicable solution to put an end to the controversy.
MoEF indicates that it was willing to grant Environmental Clearance, subject to 5 pre-conditions being met.
Lavasa agrees to the pre-conditions in order to end the issue and resume development.

Aug 2011

On 22nd August 2011, MoEF makes a statement in the High Court that they would pass the order within one week. However, the final order does not get passed

Oct 2011

In an order dated 13th October 2011, MoEF states that the decision on environmental clearance cannot be taken till all the pre-conditions, including a ‘credible action by Government of Maharashtra’, are met.

 

In the High Court hearing held on 20th October, the GoM states that they will take necessary action in accordance with the MoEF recommendations.
The court, thereafter, directs that ‘MoEF shall pass the final order within a period of three weeks and no extension will be granted to MoEF under any circumstances’.

 

The Current Status

9th November 2011

On 4th of November, State Government files a complaint in Magisterial court in Pune, thus completing all the pre-conditions set by MoEF.

Lavasa is accorded 'Environmental Clearance' by MoEF. The lifting of the status-quo allows Lavasa to resume construction and development activity.


Download Lavasa Environment clearance details in English & Marathi